CHANGE LOG

Project: National Stadium & Digital Ticketing Platform
Prepared by: Alex – Project Manager
Version: 1.0
Date: September 2028

Purpose

The Change Log ensures that all changes affecting the project are tracked and governed through the formal change control process.

The log provides traceability and transparency for stakeholders and supports Perform Integrated Change Control.

Change Log Entries

Change ID

Date Submitted

Change Description

Category

Submitted By

Impact Summary

Status

Decision Authority

CR-01

12 Feb 2026

Adjustment to WBS structure for stadium seating sections

Scope

Infrastructure Team

Minor schedule update

Approved

Project Manager

CR-02

05 Jun 2026

Addition of enhanced cybersecurity requirements for ticketing platform

Scope / Quality

Digital Security Team

Additional development effort

Approved

Change Control Board

CR-03

18 Oct 2026

Re-sequencing of steel delivery activities

Schedule

Construction Contractor

Schedule shift of 5 days

Approved

Project Manager

CR-04

10 Mar 2027

Update to ticket validation protocol for stadium entry gates

Scope / Technical

Digital Team

Gate integration testing required

Approved

Change Control Board

CR-05

22 May 2027

Increase contingency reserve due to steel market volatility

Cost

Project Manager

$1.2M contingency allocation

Approved

Steering Committee

CR-06

02 Aug 2028

Modify VIP seating configuration in West Stand

Scope

Steering Committee

Structural redesign and cost increase

Under Review

Change Control Board

CR-07

15 Aug 2028

Additional gate integration sprint for physical gate testing

Schedule

Product Owner

Sprint planning update

Approved

Project Manager

CR-08

20 Feb 2030

Adjustment of system load testing schedule before tournament launch

Schedule / Quality

IT Operations

Minor schedule shift

Approved

Project Manager

Change Categories

Changes recorded in the log may affect the following baselines:

Category

Description

Scope

Modifications to deliverables or requirements

Schedule

Changes affecting activity sequencing or milestones

Cost

Adjustments to approved cost baseline

Quality

Changes affecting standards or acceptance criteria

Procurement

Contract modifications or vendor adjustments

Change Status Definitions

Status

Meaning

Submitted

Change request recorded and awaiting review

Under Review

Impact analysis in progress

Approved

Change accepted and authorized for implementation

Rejected

Change request declined

Implemented

Approved change fully executed

Governance

Significant changes are reviewed by the Change Control Board (CCB) (a formally designated group responsible for reviewing and approving or rejecting change requests).

The CCB for this project includes:

  • Project Manager
  • Infrastructure Director
  • Digital Systems Director
  • Finance Representative
  • Ministry Steering Committee Representative