  1. Construction Progress Data

Activity ID

Activity

Planned Progress

Actual Progress

Status

C-101

Foundation excavation

100%

100%

Completed

C-102

Foundation concrete pouring

100%

100%

Completed

C-103

Structural steel installation

60%

55%

Slight delay

C-104

Roof structure assembly

25%

20%

On track

C-105

Entry gate installation

10%

10%

On schedule

  1. Digital Platform Sprint Data

Sprint

Planned Story Points

Completed Story Points

Status

Sprint 5

40

38

Near completion

Sprint 6

42

41

On track

  1. Resource Utilization Data

Resource Type

Planned Allocation

Actual Allocation

Construction Workers

120

118

Software Engineers

14

14

Security Integration Specialists

6

5

  1. Cost Data

Cost Category

Planned Cost (USD)

Actual Cost (USD)

Construction Materials

12,500,000

12,720,000

Labor Costs

3,200,000

3,150,000

Digital Platform Development

1,100,000

1,050,000

  1. Schedule Data

Milestone

Planned Date

Actual Date

Foundation Completion

10 Mar 2028

10 Mar 2028

Steel Structure Midpoint

20 Apr 2028

24 Apr 2028 (forecast)

Gate Installation Start

01 May 2028

01 May 2028

  1. Quality Data

Inspection

Result

Concrete compression test

Passed

Steel welding inspection

Passed

Security gate prototype test

Minor adjustment required

  1. Risk Event Data

Risk ID

Event

Impact

R-07

Steel delivery delay

3-day potential delay

R-11

Network instability during gate integration

Under investigation

  1. Procurement Data

Contract

Status

Steel supplier contract

Active

Ticketing platform vendor

Active

Security gate manufacturer

Delivery scheduled