PROJECT SCOPE STATEMENT

International Football Tournament Stadium & Digital Ticketing Project

  1. Document Information
  • Project Name: International Football Tournament Stadium & Digital Ticketing Project
  • Project Manager: Alex
  • Sponsor: Ministry of Sports (Inter-Ministerial Governance Committee)
  • Related Documents:
    • Project Charter (approved 25 Nov 2025)
    • Project Management Plan (approved 01 Dec 2025)
    • Scope Management Plan
    • Requirements Documentation
    • Requirement Traceability Matrix (RTM)
  • Version: 1.0
  • Baseline Date: 01 December 2025
  • Status: Approved / Baselined
  1. Project Scope Description

The project will deliver a new international-standard football stadium and an integrated digital ticketing and access-control platform to enable the successful hosting of an International Football Tournament in June 2030, while creating sustainable post-event value.

The project is executed using a hybrid delivery approach, combining:

  • predictive delivery for physical infrastructure, and
  • agile delivery for the digital ticketing solution.
  1. In-Scope Deliverables

3.1 Stadium Construction (Predictive)

  • Construction of a 50,000-seat stadium
  • Structural, safety, and accessibility compliance
  • Emergency evacuation systems
  • Physical entry gates and turnstiles
  • Stadium commissioning and certification
  • Integration interfaces for digital ticket scanning
  • Documentation required for regulatory approval

3.2 Digital Ticketing Platform (Agile)

  • Online ticket purchase functionality
  • User registration and identity verification
  • QR / digital ticket issuance
  • Real-time ticket validation at entry gates
  • Back-office reporting and monitoring dashboard
  • Cybersecurity and data-privacy controls
  • Performance and load-testing capability

3.3 Integration & Transition

  • End-to-end integration between physical gates and digital systems
  • Integrated testing and validation
  • Training for operations staff
  • Operational documentation
  • Handover to operations
  1. Out-of-Scope Items

The following are explicitly excluded from the project scope:

  • Long-term stadium operations and maintenance
  • Urban infrastructure outside the stadium boundary
  • Non-ticketing commercial platforms (merchandising, food sales)
  • Broadcasting and media production systems
  • Post-tournament event scheduling and marketing
  1. Project Deliverables

ID

Deliverable

D-01

Completed and certified stadium

D-02

Operational digital ticketing platform

D-03

Integrated access-control system

D-04

Security and compliance certification

D-05

Operations training and documentation

D-06

Formal handover package

  1. Project Acceptance Criteria

The project will be accepted when:

  • the stadium receives regulatory safety and occupancy certification,
  • the digital ticketing platform meets performance, security, and availability targets,
  • integrated testing confirms end-to-end functionality,
  • operations formally accept all deliverables,
  • governance approves project closure.

Acceptance is documented and formally signed.

  1. Constraints
  • Tournament start date: June 2030 (fixed)
  • Public-sector procurement regulations
  • Approved budget ceiling of $530 million
  • Mandatory regulatory and safety certifications
  1. Assumptions

Key assumptions include:

  • tournament dates are non-negotiable,
  • funding remains approved throughout execution,
  • key materials and vendors remain available,
  • digital adoption by spectators ≥ 85%.

Assumptions are tracked in the Assumption Log.

  1. Scope Control
  • This scope statement forms part of the Scope Baseline
  • Any change requires a formal change request
  • Scope changes are evaluated for impact on:
    • schedule,
    • cost,
    • quality,
    • risk,
    • benefits.

No work outside this scope is permitted without approval.

  1. Relationship to Benefits

All in-scope deliverables directly support benefits defined in the Benefits Management Plan, including:

  • reduced entry time,
  • improved safety,
  • fraud reduction,
  • long-term asset reuse.

Changes that do not support benefits are escalated for governance decision.

  1. Approval

This Project Scope Statement is approved and baselined.

Role

Title

Project Manager

Project Manager

Sponsor Representative

Ministry of Sports

PMO Representative

PMO

Baseline Date: 01 December 2025

 