COST BASELINE

International Football Tournament Stadium & Digital Ticketing Project

  1. Document Information
  • Project Manager: Alex
  • Version: 1.0 (Approved Baseline)
  • Approval Date: 20 December 2025
  • Status: Baseline – Controlled
  • Change Control: Formal Change Request Required
  1. Cost Baseline Summary

Component

Amount (USD)

Base Estimate

$523,000,000

Contingency Reserve

$24,000,000

Cost Baseline (BAC)

$547,000,000

Management Reserve (Excluded)

$15,000,000

Budget at Completion (BAC): $547,000,000

  1. Control Accounts by WBS Level 1

WBS

Description

Baseline Budget

1.0

Project Management & Governance

$25,000,000

2.0

Stadium Infrastructure

$464,000,000

3.0

Digital Ticketing Platform

$40,000,000

4.0

Integration & Testing

$14,000,000

5.0

Transition & Handover

$7,000,000

6.0

Project Closure

$2,000,000

Total = $547,000,000

  1. Time-Phased Budget Distribution

The budget is distributed according to the Schedule Baseline.

2025 (Planning & Mobilization)

Year

Planned Spend

2025

$18,000,000

Includes:

  • PMO setup
  • Design validation
  • Early mobilization

2026

Year

Planned Spend

2026

$85,000,000

Major drivers:

  • Site prep
  • Foundations
  • Structural works start

2027

Year

Planned Spend

2027

$140,000,000

Major drivers:

  • Superstructure
  • Roofing initiation
  • Major steel procurement

2028

Year

Planned Spend

2028

$125,000,000

Major drivers:

  • Roofing completion
  • Seating
  • Turf system
  • Digital development peak

2029

Year

Planned Spend

2029

$120,000,000

Major drivers:

  • Commissioning
  • Integration
  • Gate installation
  • Cybersecurity validation

2030

Year

Planned Spend

2030

$59,000,000

Major drivers:

  • Final testing
  • Operational readiness
  • Training
  • Transition
  • Closure
  1. Cumulative Planned Value (PV Curve)

Year

Cumulative Budget

2025

$18M

2026

$103M

2027

$243M

2028

$368M

2029

$488M

2030

$547M

This forms the Planned Value (PV) curve for EVM tracking.

  1. Contingency Allocation (Embedded)

Risk Area

Contingency Included

Steel volatility

$12M

Turf risk

$3M

Integration complexity

$4M

Regulatory delays

$5M

Total contingency: $24M
Included within control accounts.

  1. Funding Tranches

Milestone

Funding Release

Post-Charter

$50M

Post-Scope Baseline

$120M

Superstructure Start

$150M

Integration Phase

$120M

Pre-Handover

Remaining balance

  1. Earned Value Alignment

This Cost Baseline enables:

  • Planned Value (PV)
  • Cost Variance (CV)
  • Cost Performance Index (CPI)
  • Estimate at Completion (EAC)
  • Variance at Completion (VAC)

EVM will be applied at Control Account level.

  1. Governance Rules
  • Baseline change requires:
    • Impact analysis
    • Sponsor approval
    • Change Control Board decision
  • Contingency usage requires PM approval
  • Management reserve requires Sponsor authorization