COST MANAGEMENT PLAN

International Football Tournament Stadium & Digital Ticketing Project

  1. Document Information
  • Project Manager: Alex
  • Sponsor: Ministry of Sports – Tournament Steering Committee
  • Version: 1.0
  • Approval Date: 20 December 2025
  • Status: Approved / Controlled
  • Parent Document: Project Management Plan
  1. Purpose

This Cost Management Plan defines how project costs will be:

  • Estimated
  • Budgeted
  • Funded
  • Controlled
  • Reported

It establishes financial governance rules to ensure:

  • Budget discipline
  • Transparency
  • Audit readiness
  • Forecast reliability
  1. Cost Management Approach

The project uses a hybrid cost model:

Project Area

Cost Approach

Stadium construction

Bottom-up estimating + contract pricing

Turf system

Vendor-based estimate + contingency

Digital platform

Rolling-wave estimation

Integration & testing

Detailed activity-based estimation

Governance & PMO

Resource-based estimation

  1. Units of Measure
  • Currency: USD
  • Labor: USD per day
  • Materials: USD per contract or unit
  • External contracts: Lump sum or T&M per contract agreement
  1. Level of Accuracy

Project Phase

Estimate Accuracy Range

Business Case

±30%

Planning

±15%

Pre-execution lock

±10%

Execution updates

Forecast-driven

  1. Estimating Methodology

The following techniques are authorized:

  • Expert Judgment
  • Analogous Estimating (historical stadium data)
  • Parametric Estimating (cost per seat, cost per square meter)
  • Bottom-up Estimating (work package level)
  • Three-Point Estimating (for risk-sensitive elements like turf and integration)
  • Vendor quotations
  1. Cost Categories

7.1 Direct Costs

  • Construction contracts
  • Turf subcontractor
  • Gate hardware
  • Digital development vendor
  • Security audit services
  • Integration specialists

7.2 Indirect Costs

  • PMO staffing
  • Oversight consultants
  • Legal & procurement support

7.3 Contingency Reserves

Allocated for identified risks (part of cost baseline).

7.4 Management Reserve

Held outside cost baseline.
Controlled by Sponsor Committee.

  1. Cost Baseline Structure

The Cost Baseline will be organized by WBS:

  1. Project Management
  2. Stadium Infrastructure
  3. Digital Platform
  4. Integration & Testing
  5. Transition & Handover

The cost baseline will include:

  • All authorized work
  • Contingency reserves
  • Excludes management reserve
  1. Funding Requirements

Funding will be released in tranches:

Stage

Funding Release

Post-Charter

Mobilization funding

Post-Scope Baseline

Construction contract commitment

Pre-Superstructure

Major capital release

Pre-Integration

Digital vendor release

Pre-Handover

Operational transition funding

Funding schedule must align with cash-flow forecast.

  1. Cost Control

Cost performance will be monitored using:

  • Earned Value Management (EVM)
  • Cost Variance (CV)
  • Cost Performance Index (CPI)
  • Estimate at Completion (EAC)
  • Variance at Completion (VAC)

Thresholds:

Variance Level

Action

≤ 5%

Managed by PM

5–10%

Escalated to PMO

>10%

Sponsor review required

  1. Contingency Reserve Policy
  • Used only for identified risks
  • Requires PM approval
  • Must be documented in cost change log
  • Does not require sponsor approval unless threshold exceeded
  1. Management Reserve Policy
  • Controlled by Sponsor Committee
  • Used for unknown-unknown risks
  • Requires formal change request
  1. Change Control & Cost Impact

All cost impacts must include:

  • Direct cost impact
  • Schedule impact
  • Risk exposure impact
  • Funding impact

Cost baseline changes require:

  • Integrated Change Control
  • Sponsor approval
  1. Reporting

Report

Frequency

Audience

Cost Performance Report

Monthly

Sponsor Committee

EVM Dashboard

Monthly

PMO

Forecast Report

Quarterly

Ministry Finance

  1. Integration with Schedule & Scope

Cost estimates are traceable to:

  • WBS work packages
  • Activity durations
  • Risk Register
  • Assumption Log

Schedule compression decisions must include cost impact analysis.

  1. Audit & Compliance
  • All vendor payments tied to contract milestones
  • Public-sector procurement rules apply
  • External audit review quarterly
  • Cost data archived for 10 years
  1. Approval

Approved by:

  • Project Manager
  • PMO Director
  • Ministry Steering Committee

Approval Date: 20 December 2025