CHANGE REQUEST
Project: National Stadium & Digital Ticketing Platform
Change Request ID: CR-037
Date Submitted: 12 August 2028
Submitted by: Ministry Steering Committee Representative
Project Manager: Alex
- Change Title
Modification of VIP Seating Configuration in West Stand
- Description of the Change
The Ministry Steering Committee has requested an increase in VIP seating capacity within the West Stand to accommodate additional international delegation representatives attending the tournament.
The requested modification involves:
- Reconfiguring the seating layout in the West Stand
- Increasing VIP seating capacity by approximately 250 seats
- Adjusting hospitality service areas and access routes
This modification affects architectural and structural design elements that were previously approved during the design phase.
- Reason for the Change
The request arises from updated projections of diplomatic and corporate guests expected to attend the tournament.
The Ministry considers expanded VIP capacity important for:
- international relations
- tournament hosting reputation
- sponsor engagement
- Impact Analysis
Scope Impact
The modification affects the approved stadium design configuration and therefore changes the scope baseline.
Design drawings and seating layouts must be revised by the contracted architectural engineering firm.
Schedule Impact
Preliminary analysis indicates the potential for 2–3 weeks delay in construction activities in the West Stand due to:
- design review
- engineering approval
- seating fabrication adjustments
Cost Impact
Estimated cost increase:
$1,150,000
Including:
- structural modifications
- seating procurement adjustments
- architectural redesign fees
Risk Impact
New risks introduced include:
- structural compliance review delays
- seating installation sequencing disruption
- procurement timeline adjustments
Procurement Impact
The stadium construction contract assigns design authority to the engineering contractor.
Therefore, design modifications must be reviewed and approved by the contractor’s certified engineering team.
- Alternatives Considered
Option | Description |
Option A | Maintain current design (no change) |
Option B | Reconfigure seating layout with minimal structural change |
Option C | Full VIP expansion redesign (higher cost and delay) |
The Project Manager recommends Option B, which achieves the requested capacity increase with minimal structural modification.
- Recommendation
Approve a limited seating reconfiguration within the West Stand subject to formal engineering validation and updated construction sequencing.
- Change Control Board Decision
Decision | Status |
Approved | ☐ |
Rejected | ☐ |
Deferred | ☐ |
- Implementation Actions (If Approved)
- Update architectural drawings
- Revise seating procurement specifications
- Adjust construction schedule for affected work packages
- Update WBS Dictionary, Cost Baseline, and Schedule Baseline
- Project Manager Statement
This change originates from sponsor-level strategic considerations but affects areas where the project manager does not hold design authority.
Therefore, the request must be processed through formal Integrated Change Control to ensure engineering validation, contractual compliance, and controlled impact on project baselines.