MANAGEMENT RESERVE AUTHORIZATION DOCUMENT
International Football Tournament Stadium & Digital Ticketing Project
- Document Information
- Project Manager: Alex
- Sponsor: Ministry of Sports – Tournament Steering Committee
- Version: 1.0
- Approval Date: 20 December 2025
- Status: Approved – Sponsor Controlled
- Included in Cost Baseline: ❌ No
- Included in Total Authorized Funding: ✅ Yes
- Purpose
The Management Reserve (MR) is established to address:
Unidentified risks (unknown-unknowns) that are outside the scope of quantified contingency.
It exists to protect:
- Public funding credibility
- Tournament immovable deadline
- Strategic national reputation
- Amount Authorized
Component | Amount |
Cost Baseline (BAC) | $547,000,000 |
Management Reserve | $15,000,000 |
Total Authorized Funding:
$562,000,000
Management Reserve represents:
- 2.74% of total funding
- 2.74% of baseline cost
- Reasonable for mega infrastructure projects (2–5% typical)
- Ownership & Control
Management Reserve is:
- Controlled by Sponsor Committee
- Not accessible directly by Project Manager
- Released only through formal change process
The Project Manager may request MR usage but cannot authorize it.
- Conditions for Use
Management Reserve may be used only when:
- A previously unidentified risk materializes
- The impact exceeds available contingency
- The event is outside baseline assumptions
- No scope trade-off is feasible
Examples:
- New regulatory law introduced
- Geotechnical surprise not covered in risk register
- Political directive altering stadium capacity
- National security requirement for digital platform
- Prohibited Uses
Management Reserve cannot be used for:
- Poor estimating accuracy
- Scope creep without approval
- Known risks already assigned contingency
- Performance inefficiency
This distinction is critical.
- Release Process
Step 1 – PM documents:
- Nature of event
- Why it was not previously identified
- Cost impact analysis
- Schedule impact analysis
Step 2 – Impact review by:
- PMO
- Finance
- Risk oversight
Step 3 – Sponsor Committee approval required
If approved:
- Cost baseline is adjusted
- BAC increases
- Formal change recorded
- Relationship to Cost Baseline
Before MR release:
BAC = $547,000,000
After MR release (example $5M):
New BAC = $552,000,000
EVM calculations adjust accordingly.
- Monitoring & Reporting
Management Reserve status reviewed:
- Quarterly
- During governance reviews
- During major risk reassessments
Report includes:
- Remaining MR balance
- MR usage history
- Justification documentation
- Strategic Justification
The tournament start date (June 2030) is a hard constraint.
Failure to deliver has:
- International reputational impact
- Financial penalties
- Political consequences
Management Reserve ensures national-level protection.