PROJECT CHARTER
International Football Tournament Stadium & Digital Ticketing Project
- Project Identification
- Project Name: International Football Tournament Stadium & Digital Ticketing Project
- Project Sponsor: Ministry of Sports (Inter-Ministerial Governance Committee)
- Project Manager: Alex
- Authorization Date: 25 Novembre 2025
- Planned Tournament Dates: June–July 2030
- Purpose and Justification
This project is authorized to deliver:
- a new international-standard stadium, and
- an integrated digital ticketing and access-control platform
to support the hosting of an International Football Tournament and to provide long-term operational and economic benefits beyond the event.
The project is justified by the approved Business Case, which demonstrates:
- strategic alignment with national objectives,
- a positive economic return,
- and sustainable post-project benefits.
- Measurable Project Objectives
The project objectives are to:
- Deliver a 50,000-seat stadium certified for international competition by 31 March 2030.
- Implement a secure digital ticketing platform capable of handling peak demand of 60,000 users per hour.
- Reduce average spectator entry time from 45 minutes to 15 minutes or less.
- Achieve system availability of ≥99.9% during tournament operations.
- Complete delivery within the approved cost baseline of $530 million.
- High-Level Scope Description
In Scope
- Stadium construction and commissioning
- Physical entry gates and turnstiles
- Digital ticketing platform (registration, purchase, identity verification)
- Integration between physical and digital systems
- Testing, security accreditation, and operational readiness
- Handover to operations
Out of Scope
- Long-term stadium operations
- Non-tournament urban infrastructure
- Commercial merchandising platforms unrelated to ticketing
- High-Level Requirements
- Compliance with international stadium safety and accessibility standards
- Secure identity verification and fraud prevention
- Real-time access control and monitoring
- Scalability for future events
- Compliance with public procurement and data protection regulations
- Summary Milestone Schedule
Milestone | Target Date |
Project Start | November 2025 |
Stadium Construction Complete | December 2029 |
Digital Platform Ready | February 2030 |
Integrated Testing Complete | March 2030 |
Operational Handover | April 2030 |
Tournament Start | June 2030 |
- Summary Budget
Cost Category | Amount (USD) |
Stadium Construction | 460,000,000 |
Digital Ticketing Platform | 20,000,000 |
Integration & Testing | 8,000,000 |
Project Management & Governance | 12,000,000 |
Contingency Reserve | 30,000,000 |
Total Authorized Budget | 530,000,000 |
- High-Level Risks
- Construction schedule delays
- Supply-chain volatility
- Physical–digital integration challenges
- Cybersecurity threats
- Stakeholder pressure near deadlines
These risks will be further analyzed and tracked in the Risk Register.
- Assumptions and Constraints
Assumptions
- Tournament dates are fixed and non-negotiable
- Parliamentary funding approval remains valid
- Key procurement contracts can be awarded on schedule
Constraints
- Fixed delivery deadline
- Public-sector procurement regulations
- Annual budget authorization limits
Tracked in the Assumption Log.
- Project Organization and Governance
- Sponsor (Collective): Ministry of Sports Governance Committee
- Project Manager: Alex Ronaldo
- Key Stakeholders:
- Ministry of Finance
- National Infrastructure Authority
- Digital Government Agency
- Tournament Organizing Committee
Decisions follow the defined Governance Path.
- Project Manager Authority
The Project Manager is authorized to:
- apply organizational resources to project activities,
- manage day-to-day execution,
- manage approved contracts and vendors,
- approve expenditures up to $5 million per decision within the cost baseline,
- escalate issues, risks, and changes through governance.
The Project Manager does not have authority to:
- change the approved budget baseline,
- modify project scope or objectives,
- accept benefit or operational risks on behalf of the organization.
- Success Criteria
The project will be considered successful when:
- all deliverables are formally accepted,
- the stadium and ticketing platform are operationally ready,
- ownership is transferred to operations,
- and the project is closed in compliance with governance requirements.
- Approval
This Project Charter formally authorizes the project and the Project Manager.
Role | Title |
Sponsor Representative | Secretary-General, Ministry of Sports |
Finance Representative | Director of Public Investment |
Infrastructure Representative | Director of National Infrastructure |
Digital Transformation Rep. | Director of Digital Government |
Governance Chair | Inter-Ministerial Committee Chair |
Charter Approval Date: 25 Novembre 2025