PROJECT SCOPE STATEMENT
International Football Tournament Stadium & Digital Ticketing Project
- Document Information
- Project Name: International Football Tournament Stadium & Digital Ticketing Project
- Project Manager: Alex
- Sponsor: Ministry of Sports (Inter-Ministerial Governance Committee)
- Related Documents:
- Project Charter (approved 25 Nov 2025)
- Project Management Plan (approved 01 Dec 2025)
- Scope Management Plan
- Requirements Documentation
- Requirement Traceability Matrix (RTM)
- Version: 1.0
- Baseline Date: 01 December 2025
- Status: Approved / Baselined
- Project Scope Description
The project will deliver a new international-standard football stadium and an integrated digital ticketing and access-control platform to enable the successful hosting of an International Football Tournament in June 2030, while creating sustainable post-event value.
The project is executed using a hybrid delivery approach, combining:
- predictive delivery for physical infrastructure, and
- agile delivery for the digital ticketing solution.
- In-Scope Deliverables
3.1 Stadium Construction (Predictive)
- Construction of a 50,000-seat stadium
- Structural, safety, and accessibility compliance
- Emergency evacuation systems
- Physical entry gates and turnstiles
- Stadium commissioning and certification
- Integration interfaces for digital ticket scanning
- Documentation required for regulatory approval
3.2 Digital Ticketing Platform (Agile)
- Online ticket purchase functionality
- User registration and identity verification
- QR / digital ticket issuance
- Real-time ticket validation at entry gates
- Back-office reporting and monitoring dashboard
- Cybersecurity and data-privacy controls
- Performance and load-testing capability
3.3 Integration & Transition
- End-to-end integration between physical gates and digital systems
- Integrated testing and validation
- Training for operations staff
- Operational documentation
- Handover to operations
- Out-of-Scope Items
The following are explicitly excluded from the project scope:
- Long-term stadium operations and maintenance
- Urban infrastructure outside the stadium boundary
- Non-ticketing commercial platforms (merchandising, food sales)
- Broadcasting and media production systems
- Post-tournament event scheduling and marketing
- Project Deliverables
ID | Deliverable |
D-01 | Completed and certified stadium |
D-02 | Operational digital ticketing platform |
D-03 | Integrated access-control system |
D-04 | Security and compliance certification |
D-05 | Operations training and documentation |
D-06 | Formal handover package |
- Project Acceptance Criteria
The project will be accepted when:
- the stadium receives regulatory safety and occupancy certification,
- the digital ticketing platform meets performance, security, and availability targets,
- integrated testing confirms end-to-end functionality,
- operations formally accept all deliverables,
- governance approves project closure.
Acceptance is documented and formally signed.
- Constraints
- Tournament start date: June 2030 (fixed)
- Public-sector procurement regulations
- Approved budget ceiling of $530 million
- Mandatory regulatory and safety certifications
- Assumptions
Key assumptions include:
- tournament dates are non-negotiable,
- funding remains approved throughout execution,
- key materials and vendors remain available,
- digital adoption by spectators ≥ 85%.
Assumptions are tracked in the Assumption Log.
- Scope Control
- This scope statement forms part of the Scope Baseline
- Any change requires a formal change request
- Scope changes are evaluated for impact on:
- schedule,
- cost,
- quality,
- risk,
- benefits.
No work outside this scope is permitted without approval.
- Relationship to Benefits
All in-scope deliverables directly support benefits defined in the Benefits Management Plan, including:
- reduced entry time,
- improved safety,
- fraud reduction,
- long-term asset reuse.
Changes that do not support benefits are escalated for governance decision.
- Approval
This Project Scope Statement is approved and baselined.
Role | Title |
Project Manager | Project Manager |
Sponsor Representative | Ministry of Sports |
PMO Representative | PMO |
Baseline Date: 01 December 2025