RISK REGISTER
International Football Tournament Stadium & Digital Ticketing Project
- Document Information
- Project Manager: Alex
- Version: 1.0 (Post-Planning Baseline)
- Date: 15 December 2025
- Status: Active
- Review Frequency: Monthly
- Risk Rating Scale
Probability Scale
Rating | % Range |
Low | 0–20% |
Medium | 21–40% |
High | 41–70% |
Very High | >70% |
Impact Scale (Cost)
Rating | Cost Impact |
Low | < $2M |
Medium | $2–5M |
High | $5–15M |
Critical | > $15M |
- Risk Register Table
R-01 – Steel Price Volatility
- Category: Construction / External
- Description: Global steel market fluctuation increases structural cost
- Root Cause: International supply volatility
- Probability: 40% (Medium)
- Cost Impact: $30M (Critical)
- EMV: $12M
- Schedule Impact: Possible 30-day delay
- Risk Score: High
- Response Strategy: Mitigate
- Planned Response:
- Negotiate early procurement contracts
- Include escalation clauses
- Owner: Construction Lead
- Contingency Allocated: $12M
- Status: Open
R-02 – Turf Certification Rejection
- Category: Technical / Quality
- Description: Independent lab rejects turf sample
- Root Cause: Material inconsistency
- Probability: 25%
- Cost Impact: $12M
- EMV: $3M
- Schedule Impact: 14–30 days
- Strategy: Mitigate
- Planned Response:
- Pre-installation lab testing
- Vendor performance clause
- Owner: QA Lead
- Contingency: $3M
- Status: Open
R-03 – Gate ↔ App Integration Failure
- Category: Technical / Hybrid
- Description: Hardware–software interface incompatibility
- Root Cause: API misalignment
- Probability: 35%
- Cost Impact: $11.5M
- EMV: $4M
- Schedule Impact: 21 days
- Strategy: Mitigate
- Response:
- Early integration prototype
- Interface testing milestone
- Owner: Integration Lead
- Contingency: $4M
- Status: Open
R-04 – Regulatory Approval Delay
- Category: Governance
- Description: Delay in safety or occupancy approval
- Root Cause: Inspection backlog
- Probability: 30%
- Cost Impact: $16.5M
- EMV: $5M
- Schedule Impact: 30–45 days
- Strategy: Mitigate
- Response:
- Early inspection scheduling
- Pre-review audits
- Owner: PMO Compliance Officer
- Contingency: $5M
- Status: Open
R-05 – Cybersecurity Vulnerability
- Category: Digital / Security
- Description: Critical vulnerability discovered pre-launch
- Probability: 30%
- Cost Impact: $8M
- EMV: $2.4M
- Schedule Impact: 14 days
- Strategy: Mitigate
- Response:
- Independent penetration testing
- Secure coding reviews
- Owner: Digital Lead
- Contingency: Included within integration reserve
- Status: Open
R-06 – Key Resource Turnover
- Category: Organizational
- Description: Critical team member leaves mid-phase
- Probability: 20%
- Cost Impact: $3M
- Schedule Impact: 15 days
- Strategy: Mitigate
- Response:
- Knowledge transfer documentation
- Shadow assignments
- Owner: Project Manager
- Status: Open
R-07 – Extreme Weather Delay
- Category: External
- Description: Unusual weather impacts construction
- Probability: 30%
- Cost Impact: $5M
- Schedule Impact: 20 days
- Strategy: Accept + Schedule Contingency
- Owner: Construction Lead
- Status: Open
R-08 – Political Scope Expansion (VIP Seating)
- Category: Governance
- Description: Sponsor demands additional VIP capacity
- Probability: 15%
- Cost Impact: $20M
- Strategy: Avoid / Controlled Change
- Response:
- Require formal change request
- Owner: Project Manager
- Status: Open
R-09 – Digital Platform Underperformance
- Category: Technical
- Description: System fails under load
- Probability: 25%
- Cost Impact: $6M
- Schedule Impact: 10 days
- Strategy: Mitigate
- Response:
- Early load testing
- Scalable cloud infrastructure
- Owner: Digital Lead
- Status: Open
R-10 – Labor Shortage
- Category: External
- Description: Skilled labor availability declines
- Probability: 20%
- Cost Impact: $4M
- Schedule Impact: 25 days
- Strategy: Mitigate
- Response:
- Early contractor locking
- Alternative sourcing
- Owner: Construction Lead
- Status: Open
- Opportunity Risks
O-01 – Early Digital Adoption
- Probability: 40%
- Benefit: Increased sponsor revenue
- Strategy: Exploit
- Response: Early beta release
O-02 – Material Cost Stabilization
- Probability: 30%
- Benefit: Savings of $8M
- Strategy: Enhance
- Risk Exposure Summary
Total EMV (Threats):
≈ $26–28M
Contingency Allocated:
$24M
Exposure Gap: Minimal (acceptable)
- Risk Monitoring Plan
Monthly actions:
- Re-score top 10 risks
- Update EMV
- Review reserve usage
- Identify new risks
Escalation if:
- Exposure > Contingency
- Risk affects tournament milestone
- Current Status at Baseline Approval
- Total Active Risks: 10 threats + 2 opportunities
- High/Critical Risks: 4