STAKEHOLDER REGISTER
International Football Tournament Stadium & Digital Ticketing Project
Project Manager: Alex
Version: 1.0
Date: 30 November 2025
Status: Active – Updated Quarterly
1️⃣ Internal Stakeholders
S-01 – Ministry Steering Committee
- Role: Project Sponsor (collective body)
- Type: Internal / Executive
- Interest: National reputation, budget discipline, tournament readiness
- Influence: Very High
- Power: Very High
- Impact on Project: Critical
- Engagement Level: Manage Closely
- Expectations:
- On-time delivery
- No public controversy
- Transparent reporting
S-02 – Minister of Sports
- Role: Political authority
- Interest: Political success, visibility
- Power: Very High
- Influence: Very High
- Engagement Strategy: Manage Closely
- Risk: Scope pressure (VIP seating, media demands)
S-03 – Project Management Office (PMO)
- Role: Governance oversight
- Interest: Compliance, reporting accuracy
- Power: High
- Influence: High
- Engagement: Manage Closely
S-04 – Finance Authority
- Role: Budget control
- Interest: Cost discipline
- Power: High
- Influence: High
- Engagement: Keep Satisfied
S-05 – Alex (Project Manager)
- Role: Delivery accountability
- Interest: Successful execution
- Authority: Operational authority
- Engagement: Central decision-maker
2️⃣ External Construction Stakeholders
S-06 – Prime Construction Contractor
- Role: Stadium builder
- Interest: Profitability, risk transfer
- Power: High
- Influence: High
- Engagement: Manage Closely
- Risk: Contract disputes
S-07 – Turf Subcontractor
- Role: Specialized turf installation
- Interest: Certification success
- Power: Medium
- Influence: Medium
- Engagement: Monitor Closely
S-08 – Entry Gate Supplier
- Role: Hardware provider
- Interest: Integration success
- Power: Medium
- Influence: Medium
S-09 – Regulatory Authority
- Role: Safety & occupancy approval
- Interest: Compliance
- Power: Very High
- Influence: Very High
- Engagement: Manage Closely
- Risk: Approval delays
3️⃣ Digital & IT Stakeholders
S-10 – Digital Platform Vendor
- Role: Ticketing system development
- Interest: Successful deployment
- Power: High
- Influence: High
- Engagement: Manage Closely
S-11 – Cybersecurity Authority
- Role: Security clearance
- Power: High
- Influence: High
- Engagement: Keep Satisfied
S-12 – Integration Consultant
- Role: Hardware-software interface
- Influence: Medium
- Engagement: Manage
4️⃣ Tournament & Public Stakeholders
S-13 – International Governing Body
- Role: Tournament standards enforcement
- Power: Very High
- Influence: Very High
- Engagement: Manage Closely
- Risk: Turf rejection
S-14 – Sponsors & Commercial Partners
- Role: Financial contributors
- Interest: Brand exposure
- Influence: High
- Engagement: Keep Satisfied
S-15 – Fans / Public
- Role: End users
- Interest: Smooth ticketing experience
- Influence: Medium (reputational)
- Engagement: Monitor
S-16 – Media
- Role: Public communication channel
- Interest: Transparency & controversy
- Influence: High (reputational)
- Engagement: Monitor Closely
5️⃣ Organizational Stakeholders
S-17 – Functional Managers
- Role: Resource providers
- Interest: Team workload
- Influence: Medium
S-18 – Operations & Facilities Team
- Role: Future stadium operators
- Interest: Smooth handover
- Power: Medium
- Engagement: Manage
6️⃣ Stakeholder Classification (Power–Interest Grid)
Manage Closely
- Steering Committee
- Minister
- Prime Contractor
- Digital Vendor
- Regulatory Authority
- International Governing Body
Keep Satisfied
- Finance Authority
- Sponsors
- Cybersecurity Authority
Keep Informed
- Operations Team
- Functional Managers
Monitor
- Public
- Media
7️⃣ Stakeholder Expectations Summary
Stakeholder | Primary Expectation |
Minister | Political success |
Steering Committee | On-time & within budget |
Contractor | Profit stability |
Digital Vendor | Scope clarity |
Governing Body | Compliance |
Operations Team | Maintainable facility |
Public | Smooth ticketing |
8️⃣ Stakeholder Risks
Stakeholder | Risk Type |
Minister | Scope expansion |
Contractor | Contract dispute |
Regulatory Authority | Approval delay |
Governing Body | Quality rejection |
Digital Vendor | Performance failure |
Media | Reputational escalation |
9️⃣ Update Frequency
- Initial version: After Charter approval
- Updated:
- After vendor selection
- After major risk event
- Before governance reviews