WBS DICTIONARY
International Football Tournament Stadium & Digital Ticketing Project
- Document Information
- Project Manager: Alex
- Document Owner: PMO
- Related Artifacts:
- Project Scope Statement
- Work Breakdown Structure (WBS)
- Requirement Traceability Matrix (RTM)
- Project Management Plan
- Version: 2.0
- Baseline Date: 01 December 2025
- Status: Approved / Controlled
- How to Use This Dictionary
Each work package includes:
- Description (what is delivered)
- Inclusions / Exclusions (scope boundaries)
- Acceptance Criteria (what “done” means)
- Responsible Owner
- Dependencies
- Key Assumptions / Constraints
This dictionary defines scope only — not schedule or cost.
- WBS Dictionary Entries
1.0 Project Management & Governance
1.2 Project Management Planning
- Description: Development and integration of all subsidiary management plans.
- Includes: Scope, schedule, cost, quality, risk, procurement, communications, stakeholder plans.
- Excludes: Execution of project deliverables.
- Acceptance Criteria: All plans approved and baselined by governance.
- Owner: Project Manager
- Dependencies: Project Charter approval
- Assumptions: Governance availability for reviews
1.5 Integrated Change Control
- Description: Management of all project change requests.
- Includes: Change logging, impact analysis, governance decisions.
- Excludes: Informal or unauthorized changes.
- Acceptance Criteria: All changes formally approved/rejected and recorded.
- Owner: PMO
- Dependencies: PMP approval
- Constraints: Change authority thresholds
2.0 Stadium Infrastructure (Predictive)
2.1 Site Preparation
- Description: Preparation of the construction site for permanent works.
- Includes: Clearing, leveling, fencing, temporary access.
- Excludes: Permanent structures.
- Acceptance Criteria: Site readiness certificate issued.
- Owner: Construction Seller
- Dependencies: Land availability confirmation
- Assumptions: No legal disputes on site
2.2 Foundations & Structural Works
- Description: Foundations, piling, and load-bearing structures.
- Includes: Concrete works, structural steel.
- Excludes: Superstructure finishes.
- Acceptance Criteria: Structural inspection approval.
- Owner: Construction Seller
- Dependencies: Site preparation complete
- Constraints: Safety and building codes
2.3 Superstructure Construction
- Description: Construction of the main stadium structure.
- Includes: Columns, beams, slabs.
- Excludes: Roofing and enclosure.
- Acceptance Criteria: Structural completion certified.
- Owner: Construction Seller
- Dependencies: Foundations complete
2.4 Roofing & Enclosure
- Description: Installation of roof and external enclosure.
- Includes: Roofing, façade, weatherproofing.
- Excludes: Internal finishes.
- Acceptance Criteria: Stadium weather-tight.
- Owner: Construction Seller
- Dependencies: Superstructure complete
- Constraints: Weather conditions
2.5 Seating & Spectator Areas
- Description: Installation of seating and public circulation areas.
- Includes: Seats, concourses, accessibility features.
- Excludes: Commercial fit-out.
- Acceptance Criteria: Seating capacity certified.
- Owner: Construction Seller
- Dependencies: Superstructure and enclosure complete
2.6 Playing Surface – Turf System
- Description: Delivery and installation of the competition-grade playing surface.
- Includes:
- Sub-base preparation
- Drainage system
- Turf installation
- Conditioning and testing
- Certification for international competition
- Excludes: Routine turf maintenance after handover.
- Acceptance Criteria: Turf certified by authorized body for international matches.
- Owner: Construction Seller (specialist turf subcontractor)
- Dependencies: Enclosure weather-tight; utilities available
- Constraints: Seasonal/weather limits; certification standards
- Assumptions: Turf specification meets governing body requirements
2.7 Safety & Evacuation Systems
- Description: Installation of life-safety systems.
- Includes: Fire detection, alarms, evacuation signage.
- Excludes: Security surveillance.
- Acceptance Criteria: Safety regulator sign-off.
- Owner: Construction Seller
- Dependencies: Internal fit-out readiness
2.8 Entry Gates & Turnstiles
- Description: Installation of physical entry control hardware.
- Includes: Gates, turnstiles, power and network cabling.
- Excludes: Digital validation logic.
- Acceptance Criteria: Gates operational and safety-certified.
- Owner: Construction Seller
- Dependencies: Utilities available; structural completion
- Assumptions: Hardware compatible with digital platform
2.9 Utilities & Services
- Description: Installation of core utilities.
- Includes: Power, water, drainage, data backbone.
- Excludes: External city infrastructure.
- Acceptance Criteria: Utilities commissioned.
- Owner: Construction Seller
- Dependencies: Structural completion
2.10 Stadium Commissioning & Certification
- Description: Final inspections and regulatory certification.
- Includes: Safety, accessibility, occupancy certification.
- Excludes: Event operations.
- Acceptance Criteria: Occupancy permit issued.
- Owner: Infrastructure Authority
- Dependencies: All construction complete
- Constraints: Mandatory regulatory approvals
3.0 Digital Ticketing Platform (Agile)
3.1 Product Backlog Definition
- Description: Creation and prioritization of the digital product backlog.
- Includes: Feature definition and refinement.
- Excludes: Development work.
- Acceptance Criteria: Backlog approved by Product Owner.
- Owner: Product Owner
- Dependencies: Requirements Documentation approval
3.3 User Registration & Identity Verification
- Description: User onboarding and identity validation.
- Includes: Registration flows, ID verification integration.
- Excludes: Payment processing.
- Acceptance Criteria: Identity validated within SLA.
- Owner: Digital Delivery Team
- Constraints: Data protection laws
3.5 Digital Ticket Issuance (QR / Mobile)
- Description: Creation and management of digital tickets.
- Includes: QR codes, mobile ticket formats.
- Excludes: Physical ticket printing.
- Acceptance Criteria: Tickets successfully scanned at gates.
- Owner: Digital Delivery Team
- Dependencies: Ticket purchase module complete
3.8 Cybersecurity & Data Protection
- Description: Security controls and compliance.
- Includes: Encryption, access control, audits.
- Excludes: Physical security.
- Acceptance Criteria: External security audit passed.
- Owner: Security Lead
4.0 Integration & Testing
4.1 Physical–Digital Integration
- Description: Integration between gates and digital validation services.
- Acceptance Criteria: End-to-end validation successful.
- Owner: Integration Lead
- Dependencies: 2.8 and 3.x complete
4.4 Performance & Load Testing
- Description: Validation under peak load.
- Acceptance Criteria: ≥60,000 users/hour sustained.
- Owner: QA Lead
5.0 Transition & Handover
5.5 Formal Handover to Operations
- Description: Transfer of ownership from project to operations.
- Acceptance Criteria: Signed handover certificate.
- Owner: Sponsor Committee
- Dependencies: All acceptance criteria met
6.0 Project Closure
6.2 Lessons Learned Documentation
- Description: Capture and archive lessons learned.
- Acceptance Criteria: Lessons repository updated.
- Owner: Project Manager
6.5 Administrative Closure
- Description: Final administrative closure.
- Acceptance Criteria: PMO closure confirmation.
- Owner: PMO